Sunday, October 4, 2009

October 3rd Workday report





A cold morning saw 182 sheets of Gib board delivered on site. With bad weather threatening our job was to get all 182 sheets in doors and stacked in logical piles. This we did before morning tea time. There was a continuous flow of people backwards and forwards carrying one sheet at a time, with Martin directing traffic. We did it and we did it well!

Then some finished some more paint outside, others finished the scribers while all the rest began to learn how to install the wall board. We now have 175 sheets yet to go on the walls. A good day, but much harder to see the progress. 

Next week we will knock a big hole in getting the internal walls covered. Thanks to all who turned up on this cooler spring day.

Photos:

  1. No they are not praying... just making sure it is done right! Who is looking in the window?
  2. The old and the young consult on the next tasks.
  3. Dave worked in the cold outside finishing the scribers.
  4. The last sheet of Gib disappears inside. Morning tea time now!