Friday, June 13, 2008

On the home straight!


We are getting near the finish line. Just a few more weeks left to finish this house. We have put together a schedule of work to be done to help us meet our deadline. We would love as much help as we can get, check out the work to be done and feel free to join us for days of laughter, learning, and some good old fashioned hard work (well, not too hard :) ). If you need to know the address (in Dunedin) leave a comment and we'll send you an email.

7th June
Complete exterior basement cladding and sealer to interior walls and ceilings.
Remove container and cut concrete drive at top.

7th - 14th June
Complete skirtings, retaining wall and door hardware fitted.

14th – 21st June
Fit out wardrobes and sand floors.
Finish exterior work including boxing for paths.
Sand walls and ceilings, doors and windows and clean ready for painters.

21st – 28th June
Paths and concrete completed.
Painting done by painters

28th – 5th July
Heat pump fitted
Carpet and vinyl
Kitchen fitted
Garden plots and clothes line constructed
Electrical and plumbing fitoff.

5th – 12th July
Hang curtains
Finish landscaping
cleaning
Electrical and plumbing finish.

12th – 19th July
Electrical and plumbing finish and clean up.